Progress in Jharkhand, Orissa projects ‘slow’, says LN Mittal

LN Mittal has expressed concern over the slow progress in the proposed Rs1 lakh crore steel projects in Jharkhand and Orissa, but has ruled out exiting at this stage from these states

Steel king LN Mittal on Thursday expressed concern over the slow progress in the proposed Rs1 lakh crore steel projects in Jharkhand and Orissa, but ruled out exiting at this stage from the states, reports PTI.

Meanwhile, the Karnataka government has approved Mr Mittal's proposed Rs30,000-crore, six million tonnes steel project in the state and the pact will be signed in June this year.

"We are not satisfied with the progress made in Jharkhand and Orissa. We hope that we can make more progress than what we have achieved so far. But our endeavour will continue. We don't plan to exit from any of our projects," he told reporters in New Delhi.

"The plan remains the same but the project can come in phases," he said in reply to a query whether the global steel maker may scale down capacity of its 12 million tonne per annum (MTPA) plants, one each in Jharkhand and Orissa.

ArcelorMittal has been facing problems in acquiring land and delays in securing regulatory approvals for its proposed Rs1 lakh crore steel projects in Jharkhand and Orissa.

The non-resident Indian (NRI) billionaire is likely to raise these issues in a meeting with steel minister Virbhadra Singh today.

About the Karnataka project, Mr Mittal said, "The Karnataka government has given preliminary approval for the proposed plant. The Karnataka plant will be the company's third plant."




6 years ago

kind Attn,Mr.Mittal, I can provide approx.4000 acr land in jharkhand, kharswama. my idea if you cant find land together in same place ,you can go for shatelite projects, you can splite the factory ,product wise in different plases. thanks .Partha.

Deepak garg

6 years ago

Dear LN Mittal Sir
we have 7400 Acres land with all villagers NOC sign in Jharkhand (where u start ur new plant) we read ur this plant news in newspaper & start for searching land in same area; from some time i search ur contact information; so pls tell me where we show land document.. urently

Shadi Katyal

6 years ago

It is indeed very thoughtful of Mr. Mittal to bring such project but how long will he have to wait.Evidently Mr. Dubey you are not a businessman. You think his personal meeting will solve the problem,
People have to understand that if they wish to live better life, they might have to sacrifice their land which not only keeps them in poverty but have no future to move ahead. Other wise these people would not be so poor. We have seen similar situation in Bengals with TATA NANO.
What Govt needs is to negotiate if the state wants any plkant with people and show some respect for the farmers and not Sarkari toughness.
India can only progress if people are shown the true picture and not exploited by.NGO and other groups.

vivekanand dubey

6 years ago

First off i am very happy for Mr.Mittal statement he not quit this state. I would like to draw his concentation diectly meet the person and slove thier problem regarding land,because every need thier bread and grant their future bread through this coming steel plant. By the bless of the god you will make the plant in jharkhand and orrisa. By it you will give the power of india through this mega project. Belive in god you will do it shortly.

Shadi Katyal

7 years ago

Maybe the contributions to bureaucracy is not enough. Who cares for the poor people after all our Ministers the poorest

Coal supply shortage threatens four NTPC stations

With the State-run company’s Farakka, Talcher and Khalagaon units already on the coal shortage list for a long time, its Durgapur unit is a new addition

State-run power producer National Thermal Power Corporation (NTPC) continues to face serious coal supply shortage at four of its plants. Central Electricity Authority (CEA) has added NTPC’s Durgapur unit to the super-critical list of thermal power plants which are facing coal supply shortage. Usually, thermal power plants which have coal supply for less than four days are included in the super-critical list.

NTPC’s Farakka, Talcher and Kahalagaon units have been facing the same problem since the past few months.

According to the CEA website, as on 5 January 2010, Farakka and Kahalagaon were reported to have zero day coal supply. In addition, NTPC’s Talcher and Durgapur units had supplies for less than four days. 

CEA has cited delay in imports as the main reason for critical coal stocks at the Farakka, Kahalagaon and Talcher units and unloading constraints for the critical coal stock position at Durgapur.

Earlier, in its quarterly list published in September, CEA had listed NTPC’s six thermal power stations in the critical list. Out of these units, situation at three units has improved in December. However, for the rest of the units, coal supply remains to be in a critical stage.

NTPC’s Farakka, Khalagaon, Sipat, Badarpur, Tanda, Talcher and Vindhyachal stations were on the critical list in September, where these units had coal supply for less than seven days.

Although the Sipat, Badarpur, Tanda and Vindhyachal units have shown marginal improvement, coal supply at these units continues to be less than the normal required quota in terms of the number of days. Farakka, Talcher and Kahalagaon, on the other hand, continue to be in the super-critical list.

Based on the September data, Moneylife had sent a mail to NTPC. In a reply, an official said,” The coal situation has improved in all these mentioned stations so has the generation.”  However, the same official was not immediately available for comments on the new, updated data.

NTPC owns the Durgapur unit through a joint venture. The plant has a capacity of 120 megawatts (MW). The Talcher plant in Orissa has a capacity of 3,000MW and the Kahalagaon plant in Bihar has a capacity of 2,340MW.

During FY10, CEA expects NTPC's capacity addition to be 1.2 gigawatts (GW) against the company's target of 3.3GW. Until October 2009, NTPC had commissioned only 500MW at its Kahalgaon unit.

The company has signed a memorandum of understanding with the government of Chhattisgarh to set up a 4GW coal-based thermal power project (five 800MW units) at Lara in Raigarh district.

The company has been allotted the Talaipalli coal block in Chhattisgarh with minable reserves of 600 million tons. However, according to a recent review by CEA, the mining plan for the block has still not been approved.

During the 11th five-year plan period, NTPC had commissioned 3.2GW of capacity, and 17.9GW of capacity is under construction, including eight super-critical units of 660MW, and 3GW of projects are yet to be awarded.


I made a living doing what I wanted to do and I am willing do it all over again

Prof Man Mohan Sharma is one of India’s most decorated teachers and a global figure in the...

Premium Content
Monthly Digital Access


Already A Subscriber?
Yearly Digital+Print Access


Moneylife Magazine Subscriber or MSSN member?

Yearly Subscriber Login

Enter the mail id that you want to use & click on Go. We will send you a link to your email for verficiation

We are listening!

Solve the equation and enter in the Captcha field.

To continue

Sign Up or Sign In


To continue

Sign Up or Sign In



The Scam
24 Year Of The Scam: The Perennial Bestseller, reads like a Thriller!
Moneylife Magazine
Fiercely independent and pro-consumer information on personal finance
Stockletters in 3 Flavours
Outstanding research that beats mutual funds year after year
MAS: Complete Online Financial Advisory
(Includes Moneylife Magazine and Lion Stockletter)