Citizens' Issues
Public Interest Exclusive
Mumbai Metro project attracts modifications by Centre

Following a Moneylife article published on the Mumbai Metro project, and its wide distribution among all stakeholders, the Centre has sought modifications

 “Mumbai Metro Line 3 – Some Questions need to be asked” published about a fortnight back in these columns seems to have had its effect. Certain modifications have been sought by the ministry of urban development, Government of India. However the key question of implementing the Mumbai Metro has not been addressed. There seems to be no integrated plan of the Metro project as it seems to be encountering one hurdle after the other which could have been envisaged in advance but has not been done. Even the Dadar railway station makeover seems to be only a makeover plan and does not envisage getting the Western Railway and Central Railway tracks and trains integrated.

The last week of February was quite an interesting week from the Mumbai’s transportation infrastructure and urban development perspectives. Firstly, the week began with the team from Government of Maharashtra (GoMah) and Mumbai Metropolitan Region Transport Authority (MMRDA) visiting Delhi to get the green signal from the finance ministry, Government of India (GoI)–after all the latter were to provide 15% of the project cost of Rs21,000 crore for the 37.5 km Colaba-BKC-Airport-SEEPZ fully underground Metro rail line (Line No 3 of the Mumbai Metro Master Plan) which would be the first underground Metro rail service in Mumbai. Several questions are needed to be asked before proceeding with the project. Even the very need of such high end expensive poorly serving infrastructure is needed to be investigated. This column had thrown up several questions in the recent past article. That article had highlighted the inadequacy of capacity, very high costs and very long duration for implementation. Apparently the team came back with a tentative nod—what that means is anybody’s guess. However, what seems to be certain is that the team from Mumbai was asked to consider running nine coach trains and get back to them. This seems to be a stalling game or face-saving option to the team. By running nine coach trains with capacity of 300 per coach running every three minutes would mean a throughput of 60/3 x (9 x 300) = 54,000 pphpd and two of these routes would make it 108,000 pph as against the need of 1,80,000 pph. 300 persons per coach actually means a crush density of six standing persons per square meter. The coach is to be designed for a peak period crush load of eight standing persons per square meter. This comes to 360 persons per coach along with the seated commuters. This brings the capacity to 9 x 360 x (60/3) x 2,  i.e. about 1,30,000 pph for two routes, much closer to the required capacity of 1,80,000 pph yet 50,000 pph in short supply. Alas, it will be available only about 30 years hence.

What does that mean? It simply means longer underground station lengths and longer rakes and larger stabling yards and car sheds; higher capacity of disaster mitigation and management (DMM) facilities and maintenance manpower, etc. It means nearly 50% higher costs. Since fare-box collection will not be able to meet even the operating expenses and recovery of investment is possible through realty development, naturally it will be possible only by further densification of the already dense city. Thus the requirement is being increased, but not commensurate with the increase in capacity which has a shortfall in any case. Did the ministry of urban development and ministry of finance raise any of the points raised in the said column?

The referred article was in fact sent to all stakeholders; Government of India and Maharashtra, MMRDA and also Maharashtra chief minister Prithviraj Chavan. Apparently the points raised therein were taken up for discussion and there is hope that some positive steps would be taken to make the transportation sustainable in Mumbai, that importance will be given to walking, cycling and the BRTS.

Following the news on Line 3 came the news that Line No 2 of the MMMP from Charkop to Mankhurd via Bandra may altogether get cancelled because it has to go underground or on the surface in the vicinity of the Juhu Aerodrome. The 32 km elevated metro will be too expensive to go underground despite the knowledge that if one includes socio-economic costs, underground Metro is a better option.

By this date in 2012, Line 1, Line 2 and Line 3 should have been in operational stage; the reality is that even Line 1 may not get ready by 2013.

Going by the crowd considered in the Metro to show how it will reduce the load on railways, it is going to be nowhere near as comfortable to travel as being projected. In fact in Delhi Metro peak time travel, the crowd must have been barely four persons per sq meter when the air-conditioning failed to function well. It will be dreadful to imagine how uncomfortable travel will be in Mumbai when the load is even six persons per sq meter crush load, leave aside 8 p/m2 peak crush load.

There is good news in the transportation sector in connection with accessibility of railway system to Persons with Disability (PwD). The public interest litigation (PIL) on this matter in the Bombay High Court came for hearing. While The Persons with Disabilities (Equal Opportunities, Protection of Rights and Full Participation) Act came into existence in 1996, the details of physical built environment was prepared by Central Public Works Department (CPWD) of the ministry of urban development (MoUD) only in 1998 and around the same time even the Research, Designs, Standards Organisation (RDSO) of the ministry of railways brought out their standards. Railways have not been following this Standard uniformly. To assist railways, especially the Western Railway and the Central Railway on their suburban services in Mumbai, in planning and implementing as well as monitoring, a high court committee has been formed comprising of the two petitioners, one of whom is blind and the other is wheelchair-based, four persons with technical and architectural expertise, four officers from WR and CR each and one from the RDSO. Optimism prevails in that the committee will work towards the set objective sincerely, systematically, diligently and over a finite time, make the railway system accessible to PwD. If the system is adequately friendly towards PwD, travel to other commuters will also be easier, provided of course the overall commuter demand does not exceed so exorbitantly as at present. Plans are afoot to increase transportation capacities significantly by way of Metro rail, BRTS, etc, to reduce excessive load on the railways.

While CR suburban trains running on the WR tracks is limited only to the Harbour Line from Mahim to Andheri, the twain do not criss cross at Dadar although they do come sufficiently close to each other to do this switchover. For some similar reason the Suburban Main and Harbour Lines do not cross over to facilitate Fast Local from CST to Kurla and Navi Mumbai. Whatever these reasons are, they are not widely known—perhaps not known at all! However, the good news is that the Dadar stations of WR & CR will undergo a sea change when they build roof plazas and 25 entry points. It is hoped that it will be friendly to PwD. Also, while it is expected to provide parking space for 800 cars, it will provide enough space for bicycle parking. It is also hoped that the planners will consider a roadway at the plaza-level parallel to the tracks, starting from the Tilak Bridge and connecting the Elphinstone Bridge on which there will be an up and down dedicated bus lane and a lane with no halt for cars. Only the cars which are parked in the parking lot will be allowed to use this lane.

Actually space for car parking should not be there at all. Parking facility for bicycles and at most motorized two-wheelers should be provided with parking facility. Of course, a bicycle lane must also be provided. It is naturally expected that a plaza will have adequate walking infrastructure. At the same time they should connect the WR and CR tracks have crossings so as to enable western suburbs’ commuters come up to CST and eastern suburbs’ commuters go up to Churchgate. At the same time have a ‘reversing’ platform whereby, like that at Wadala, so that eastern suburbs get access to western suburbs and vice versa without having to alight and cross over the FOB, etc.

(Sudhir Badami is a civil engineer and transportation analyst. He is on Government of Maharashtra’s Steering Committee on BRTS for Mumbai and Mumbai Metropolitan Region Development Authority’s Technical Advisory Committee on BRTS for Mumbai. He is also member of Research & MIS Committee of Unified Mumbai Metropolitan Transport Authority. He was member of Bombay High Court appointed erstwhile Road Monitoring Committee (2006-07). While he has been an active campaigner against noise for more than a decade, he is a strong believer in functioning democracy. He can be contacted on email at [email protected])


Personal Finance Exclusive
Life Insurance: Protecting wisely

Insurance is mainly an investment vehicle now. Can we look beyond?

It is good to see a host...

Premium Content
Monthly Digital Access


Already A Subscriber?
Yearly Digital+Print Access


Moneylife Magazine Subscriber or MSSN member?

Yearly Subscriber Login

Enter the mail id that you want to use & click on Go. We will send you a link to your email for verficiation
India Infoline Finance gets PFRDA approval to act as NPS aggregator

The PFRDA approval will enable IIFL Finance to distribute pension products under PFRDA NPS - LITE primarily targeting marginal investors and promote small savings among the public investors through its various branches and offices.

India Infoline Finance (IIFL Finance) received registration from Pension Fund Regulatory and Development Authority (PFRDA) to act as ‘Aggregator’ under National Pension System (NPS).

This will enable IIFL Finance to distribute pension products under PFRDA NPS - LITE primarily targeting marginal investors and promote small savings among the public investors through its various branches and offices.

R Venkataraman, director, IIFL Finance said, “IIFL’s strong distribution network and a large retail client base will help in distributing these pension products to the vast public in an efficient manner and provide continuous support services in this growing segment.”


We are listening!

Solve the equation and enter in the Captcha field.

To continue

Sign Up or Sign In


To continue

Sign Up or Sign In



The Scam
24 Year Of The Scam: The Perennial Bestseller, reads like a Thriller!
Moneylife Magazine
Fiercely independent and pro-consumer information on personal finance
Stockletters in 3 Flavours
Outstanding research that beats mutual funds year after year
MAS: Complete Online Financial Advisory
(Includes Moneylife Magazine and Lion Stockletter)